We were able to pick up all of our plumbing fixtures this week. Everything is being stored in the old dining room and it resembles a Kohler store room. Cindy of Ram Marketing (Kohler Representative) was able to work with us and we selected everything from their lines for the Kitchen and the two Bathrooms. I can hardly wait to have everything installed as there is some pretty cool pieces. Probably my favorite will be our kitchen taps. For a quick view go to www.kohler.com and search for 'karbon'

This past week saw the plumbing and heat lines from the second floor through the main floor and down into the basement. Hopefully by the end of this coming week we will have more things connected.
The next shot is the ceiling of the kitchen. We will have lots of natural light from the two windows but we will also have ample light from all of the pot lights and pendants. The pendants need to be selected this week but we have a good idea of what we want.