The current Hydro Meter is located right where the new exterior wall is to be located. As soon as the foundation is done the wall framing will hopefully follow
rapidly. To ensure that there are no additional delays, the Hydro Meter needs to be relocated. When I spoke with MB Hydro they suggested that the new temporary meter needs to be located on a 6x6 post with the feed at least 10'-0" to 12'-0" above the ground. I don't want to locate the post just anywhere's so the idea was to incorporate the post as part of the structure for the future deck and pergola. To do that we need to come up with a design as to what the structure might look like. Below is round #1 in the design and who knows this might be the actual build!!!
The Smaller image is of the potential side elevation of the pergola in green in comparison to the renovated house. This definately warrants a deeper design solution - I like it.